Town of Berlin, Alabama
Annual Transportation Plan
FY2023-2024
(Rebuild Alabama Act# 2019-2)
Total Expected Revenue 4th year- $16,000
Project Details: Project improvements include roadway widening, reconstruction and resurfacing on County Road 1614 from Alabama Highway 278, northward, to an approximate location for future access to the Berlin Municipal Complex. This includes realignment of the intersection at County Road 1614 with County Road 1615. The Point of Origin starts at County Road 1614 from Alabama Highway 278, intermediate points of access include the farmers market and town hall facilities, and the destination is the approximate location for future access to the Berlin Municipal Complex.
Total Project Cost: $350,000
Funding Summary:
RRA Funds: $16,000
FY2024 Rebuild Alabama Grant: $250,000
Road Fund & General Fund: $84,000
ADOPTED AND APPROVED by the Town of Berlin Town Council this the 21st day of August 2023.