Town of Berlin, Alabama

Annual Transportation Plan

FY2024-2025

(Rebuild Alabama Act# 2019-2)

Total Expected Revenue 5th year- $16,000

Project Details: Project improvements include roadway widening, reconstruction and resurfacing on County Road 1614 from Alabama Highway 278, northward, to an approximate location for future access to the Berlin Municipal Complex. This includes realignment of the intersection at County Road 1614 with County Road 1615. The Point of Origin starts at County Road 1614 from Alabama Highway 278, intermediate points of access include the farmers market and town hall facilities, and the destination is the approximate location for future access to the Berlin Municipal Complex.

 

Total Project Cost: $350,000

Funding Summary:

           RRA Funds: $16,000

FY2024 Rebuild Alabama Grant: $250,000

Road Fund & General Fund: $84,000

ADOPTED AND APPROVED by the Town of Berlin Town Council this the 19th day of August 2024.