Town of Berlin, Alabama
Annual Transportation Plan
FY2025-2026
(Rebuild Alabama Act# 2019-2)

 

Total Expected Revenue 6th year- $17,000

Project Details: Project improvements include roadway widening, reconstruction and resurfacing on Mt. Carmel Drive from US Highway 278, northward, continuing onto a portion of County Road 1614 for future access to the Berlin Municipal Complex. This includes realignment of the intersection at County Road 1615. The Point of Origin starts at Mt. Carmel Drive and US278/AL74. Intermediate points of access include the farmers market and town hall facilities, and the destination is the approximate location for future access to the Berlin Municipal Complex.

Total Project Cost: $386,254.50

Funding Summary:

RRA Funds: $45,586.35

FY2025 Rebuild Alabama Grant: $295,627.25

Road Fund & General Fund: $37,629.82

ADOPTED AND APPROVED by the Town of Berlin Town Council this the 18th day of August 2025.